New Trier Board approves to start with bid package deal for new $75-million athletic facility function to commence this summer months

Work on New Trier’s $75-million project to replace its historic Gates Gymnasium is relocating ahead as planned, university officials mentioned throughout the board of education’s June conference. 

District officers are “well underway” with structure and scheduling work associated to the job and options are now producing their way in entrance of the Village of Winnetka for needed approvals, according to Chris Johnson, New Trier’s affiliate superintendent. 

Johnson offered board customers with an update on the project’s standing, noting that “really exciting progress is remaining created.” 

At the conference, the board accepted the project’s 1st bid offer for $884,902. That offer contains three trades: electrical, mechanical and site work, according to a memo from Johnson, who additional utility and web site preparation get the job done will be carried out this summer time. 

That do the job will entail “relocating electrical and natural gas lines, switching the existing pool dehumidification and pool heating system off the steam boilers which will be demolished, and putting in a new electrical generator,” Johnson stated in the memo.

The District 203 Board of Training authorized a $75-million challenge earlier this 12 months to replace New Trier Higher School’s Gates Gymnasium. The new three-story facility could be finished in August of 2023.

Officials reported the bids for the remaining get the job done will be sent out in two substantial-scale deals in the fall that will make up the greater part of do the job. In complete, more than $60 million worthy of of operate will be bid out for the project, officers reported.

The first package deal of perform is starting off before long for the reason that it will “facilitate a clean formal start off to design in December 2021,” Johnson mentioned. The district also prefers the work be finished in the summer months so the impression on college students and personnel, and the school’s understanding natural environment, is minimal. 

Back in February this year, the district’s board of education and learning unanimously authorised the $75-million challenge that will demolish the school’s historic health club and reimagine the east facet of the substantial school’s campus, as earlier documented by The Record.

Strategies contact for the design of a new, a few-tale athletics and kinetic wellness facility that will deal with what officers called a “glaringly obvious need” resulting from “underinvestment about quite a few several years.”

The project features a new levels of competition health club, six-lane indoor observe, synthetic turf industry, cardio and weight-coaching spaces, several auxiliary fitness centers, and 12 new educational understanding areas, 8 of which will be classrooms.

Building on the project is slated to start in December of this yr with a target completion date of August 2023.

For a in depth breakdown of the plan, go through the Record’s previous coverage of this story below.

For each Johnson, the layout improvement stage of the project is ongoing. He observed this is the phase where officers are “really receiving the style and design established in wide terms.” 

This stage will possible continue until finally the close of June, in accordance to officials. When it is concluded, the district will commence getting ready plans for permitting and further more bidding documents, Johnson mentioned. 

The conclusion of the style and design improvement procedure is consistently the level in which a new price estimate is produced, in accordance to Johnson. He stated the charge estimate adhering to the period should be concluded by the conclusion of June. 

New Trier Higher School’s Gates Gymnasium, a facility officers described as out of date and much too compact for the wants of today’s students, will be demolished and changed with a new facility.

New Trier options to develop two price tag estimates, one particular done by the project’s construction management corporation and the other by an independent expense estimator. The entities will then meet collectively to provide the district with a final value estimate, according to officers. 

Johnson said if the price tag estimate exceeds the beforehand established $75-million spending plan, the district, together with the construction and structure firms, will do the job to decide ways “to retain the primary budget.”

The job is also at the moment undergoing a protection evaluation to make certain what officers explain as the development of “a facility that provides a safe educational natural environment for (New Trier) learners, employees and site visitors.” 

Areas in the course of the new facility will be developed to “support specified harmless regions and to have simple egress in circumstance of unexpected emergency,” Johnson claimed. “They will also involve electronic doorway locks, constructing isolation technological know-how, safe vestibules and shatter resistant glass.” 

The task requires many approvals from the Village of Winnetka — which officers said is normal for massive building initiatives, especially at New Trier. It will want to show up in front of Winnetka’s Zoning Board of Appeals, Style Review Board, Prepare Fee and Village Council. 

Final approval from the Village could come as soon as July 6, for every Johnson, who observed it could also get stretched out to the commencing of August. 

“It’s largely no matter if we can get all the ideal folks jointly for meetings and (that) they have the info that they require,” he said.


The File is a nonprofit, reader-funded information web site. Our general public-assistance journalism is free for all to go through.

Become a subscriber for whole entry to our neighborhood information and to help The History.

Just want to assist? You can donate to The Report at any time.